In a perfect world, the construction contract that you enter into should be prepared with the
goal of protecting your interests, not those of the owner or general contractor. In real life,
however, you are usually given a pre-printed AIA or AGC form, or even one that has been
prepared by the owner/contractor, and you are left with the impression that no modifications
to the contract will be permitted.
it is very important that you review and understand all of the contract’s terms and conditions.
Failing to do so may lead to adverse consequences such as:
inattentive subcontractor may find in a contract. The goal of these articles is to make you aware
of some of the pitfalls that you may face, with the hope that you implement a procedure to
evaluate each construction contract prior to signing and to handle disputes should they arise
during performance of the work.
disbursement of progress payments, retention and final payment. These provisions generally
require payment from the owner before the contractor will release funds to the subcontractor.
They typically fall into one of two categories: (a) “pay-when-paid” clauses; or (b) “paid-if-paid”
clauses. Although they sound similar, these clauses can have a significantly different impact on
the subcontractor.
make payment to the subcontractor within a reasonable time regardless of whether the owner
makes payment to the contractor.
contractor is obligated to make payment to the subcontractor. The contractor is excused from
making payment to the subcontractor if the owner does not pay the contractor. The risk that the
subcontractor undertakes is significantly different depending upon which clause is in the
subcontract. Under a “pay-when-paid” clause, the contractor bears the risk of nonpayment by
the owner. In contrast, it is the subcontractor, not the contractor, who bears the risk of the
owner’s non-payment under a “pay-if-paid” clause. This “risk” exists regardless of whether the
owner’s nonpayment is the result of the owner’s insolvency or bankruptcy, the owner skipping
town, the owner’s refusal to pay for “unauthorized” extra work, or even the owner’s dispute with
the contractor over unrelated issues or projects.
fees if the parties have to litigate or arbitrate their dispute. There are generally two types of
attorneys’ fees clauses: (a) “prevailing party;” and (b) “non-reciprocal.” The “prevailing party”
clause allows the party who wins the dispute to recover its attorneys’ fees from the losing party.
A “non-reciprocal” clause, however, only allows one of the parties, typically the contractor, to
recover its attorneys’ fees – even if the other party wins the dispute.
provisions. Construction subcontracts often contain language that bind the subcontractor to other
documents or other obligations that are not specifically outlined in the subcontract. Here are two
examples:
incorporated into the provisions of the subcontract. The second provision is known as a
“Flow-Through Clause.” It essentially passes on to the subcontractor some or all of the
obligations that the contractor has to the owner, but it does not necessarily give the subcontractor
the same rights against the contractor that the contractor may have against the owner.
subcontractor is successful at negotiating an arbitration or liquidated damages clause out of the
subcontract, those efforts may be rendered meaningless if the prime contract requires arbitration
or permits the assessment of liquidated damages.
a dispute, that require you to provide notice of certain events, and that place limitations on your
ability to recover additional compensation.
Douglas Colville is a Partner with the law firm of Dymond • Reagor • Colville, LLP.
—————————————————————————————————————————–